General Information

Beginning of works: 1998
Completion: 2002
Status: in use

Project Type

Location

km Name
Show coordinates on a map

Technical Information

Dimensions

total length 59.4 km

Quantities

structural steel 63 000 t
concrete volume 258 547 m³

Cost

cost of construction United States dollar 385 000 000

Chronology

24 September 1998

Beginning of construction.

September 2002

Expected opening.

13 September 2023

End of concession agreement.