General Information
Other name(s): | Havelbrücke Plaue |
---|---|
Beginning of works: | 2000 |
Completion: | 2002 |
Duration of works: | 27 months |
Status: | in use |
Project Type
Structure: |
Box girder bridge |
---|---|
Function / usage: |
Road bridge |
Structure: |
Haunched girder bridge |
Material: |
Steel-reinforced concrete composite bridge |
Location
Location: |
Plaue an der Havel, Brandenburg an der Havel, Brandenburg, Germany |
---|---|
Crosses: |
|
Carries: |
|
Coordinates: | 52° 24' 43.39" N 12° 25' 30.62" E |
Technical Information
Dimensions
main span | 70.00 m | |
total length | 240.00 m | |
span lengths | 14.00 m - 50.00 m - 70.00 m - 50.00 m - 35.00 m | |
number of spans | 5 | |
bridge surface | 3 180 m² | |
deck | width | 13.25 m |
Quantities
superstructure | structural steel | 593 t |
concrete volume | 1 166 m³ | |
reinforcing steel | 266 t |
Cost
cost of construction | Euro 3 800 000 |
Materials
girder |
steel
|
---|---|
deck slab |
reinforced concrete
|
Participants
Owner
Client
Design
Structural engineering
Checking engineering
- Michael Mündecke (checking engineer)
Co-contractor
Formwork
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Brücken und Tunnel der Bundesfernstraßen 2004. Deutscher Bundes-Verlag, Berlin (Germany), 2004, pp. 51-64.
- Die Havelbrücke im Zuge der B1 - Ortsumgehung Plaue. In: Stahlbau, v. 71, n. 10 (October 2002), pp. 727-734. (2002):