General Information

Completion: 2002
Status: in use

Project Type

Location

Location: , ,
Crosses:
  • Nitelva River
Coordinates: 59° 57' 8.32" N    11° 2' 13.97" E
Show coordinates on a map

Technical Information

Dimensions

span lengths 26.760 m - 18.900 m
number of spans 2

Materials

deck prestressed lightweight concrete (LC 60)

Chronology

September 2002

In two 24-hour periods where train traffic is completely stopped on that part of the railroad line, a precast span is transported to the site and suspended above the existing steel span using special transport bogies and DYWIDAG prestressing bars. The rails are cut at each end of span and the existing span below is then attached to the precast span using prestressing bars. The steel part is cut into three parts to be able to lower it onto a barge. As the new deck is shallower, the supports are heightened and then the new span is lowered into its final position. Railroad traffic is resumed after ballast and rails are put in place. This procedure was done for each span.

Participants

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20012535
  • Published on:
    26/07/2004
  • Last updated on:
    05/02/2016
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine