General Information
Name in local language: | Viaducto de Navia |
---|---|
Beginning of works: | 2003 |
Completion: | 2 July 2006 |
Status: | in use |
Project Type
Structure: |
Axial (single) tied-arch bridge |
---|---|
Function / usage: |
Motorway bridge / freeway bridge |
Material: |
main bridge: Steel-prestressed concrete composite bridge |
Construction method: |
deck: Precast segmental construction using launching gantry |
Material: |
Structurae Plus/Pro - Subscribe Now! approach viaducts: Prestressed concrete bridge |
Location
Location: |
Navia, Asturias, Spain Coaña, Asturias, Spain |
---|---|
Address: | A-8 |
Part of: | |
Coordinates: | 43° 31' 44.49" N 6° 43' 27.24" W |
Technical Information
Dimensions
total length | 905.4 m | |
span lengths | 46.3 m - 70 m - 3 x 75 m - 2 x 160 m - 75 m - 67.5 m - 60 m - 41.6 m | |
number of spans | 11 | |
horizontal radius of curvature | 1 540 m | |
precast elements (RC) | width | 10.7 m |
approach viaducts | ||
---|---|---|
deck | deck width | 23.1 m |
girder depth | 3.7 m | |
main bridge | ||
arches | rise | 35.43 m |
deck | deck width | 27.0 m |
Materials
deck |
precast prestressed concrete
|
---|---|
piers |
reinforced concrete
|
arches |
concrete-filled steel section
|
abutments |
reinforced concrete
reinforced concrete |
hangers |
steel wire
|
Participants
Contractor
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Viaducto de Navia. In: Hormigón y acero, v. 59, n. 250 (4th Quarter 2008), pp. 7-37. (2008):
- Viaducto de Navia (1) proyecto. Presented at: IV Congreso de la Asociación Científico-Tecnica del Hormigón Estructural - Congreso Internacional de Estructuras, Valencia, 24-27.11.2008. (2008):
- Viaducto de Navia (2) construcción. Presented at: IV Congreso de la Asociación Científico-Tecnica del Hormigón Estructural - Congreso Internacional de Estructuras, Valencia, 24-27.11.2008. (2008):
- About this
data sheet - Structure-ID
20048565 - Published on:
07/10/2009 - Last updated on:
25/04/2017