General Information
Official designation: | BW 5 |
---|---|
Beginning of works: | January 2015 |
Completion: | December 2016 |
Status: | in use |
Project Type
Function / usage: |
Road bridge |
---|---|
Structure: |
Single T-section girder bridge |
Material: |
Prestressed concrete bridge |
Support conditions: |
for registered users |
Plan view: |
Structurae Plus/Pro - Subscribe Now! |
Material: |
Structurae Plus/Pro - Subscribe Now! |
Location
Location: |
Bad Salzungen, Wartburgkreis, Thuringia, Germany |
---|---|
Address: | B62n |
Coordinates: | 50° 48' 19.36" N 10° 11' 57.40" E |
Technical Information
Dimensions
total length | 201.00 m | |
span lengths | 36.00 m - 3 x 43.00 m - 36.00 m | |
number of spans | 5 | |
bridge surface | 2 331.60 m² | |
deck | deck depth | 2.00 m |
deck width | 11.60 m | |
roadway / carriageway width | 8.00 m | |
piers | width | 3.30 m |
thickness | 1.20 m | |
pile caps | width | 4.20 m |
length | 6.60 m | |
piles | diameter | 1.20 m |
Quantities
piles | concrete volume | 300 m³ |
reinforcing steel | 30 t | |
substructure | concrete volume | 950 m³ |
reinforcing steel | 120 t | |
superstructure | concrete volume | 2 325 m³ |
prestressing steel | 85 t | |
reinforcing steel | 300 t |
Design Loads
live load | LM1 | |
design code(s) | DIN EN 1991-2 |
Cost
cost of construction | Euro 3 900 000 |
Materials
deck |
prestressed concrete
(C 35/45)
|
---|---|
piers |
reinforced concrete
(C 30/37)
|
abutments |
reinforced concrete
(C 30/37)
|
Participants
Owner
Client
Design
Structural engineering
Soil investigation report
Checking engineering
- Ekkehard Fehling (checking engineer)
Contractor
Construction management
Site supervision
Relevant Web Sites
Relevant Publications
- Brücken und Tunnel der Bundesfernstraßen 2022. Bundesministerium für Verkehr und digitale Infrastruktur, Berlin (Germany), 2022, pp. 89-101.
- About this
data sheet - Structure-ID
20072162 - Published on:
17/11/2016 - Last updated on:
20/04/2023