General Information

Beginning of works: 29 September 2007
Completion: 17 February 2011
Duration of works: 41 months
Status: in use

Project Type

Structure: Tunnel
Function / usage: Road tunnel
Construction method: Cut-and-cover method

Location

Location: , , ,
Coordinates: 47° 58' 38" N    8° 49' 6" E
Coordinates: 47° 58' 48" N    8° 48' 24" E
Show coordinates on a map

Technical Information

Dimensions

length 948 m
clear interior profile 9.70 m x 5.00 m
piles number 1 700

Quantities

concrete volume 27 000 m³
reinforcing steel 4 300 t
volume of extracted material 145 000 m³
shotcrete 20 000 m³

Cost

cost of construction ca. Euro 31 000 000

Relevant Web Sites

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20064777
  • Published on:
    20/03/2013
  • Last updated on:
    25/07/2014
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine