General Information
Other name(s): | Talbrücke Kochenbach |
---|---|
Status: | in use |
Project Type
Structure: |
Girder bridge |
---|---|
Function / usage: |
High-speed rail bridge |
Material: |
Steel-reinforced concrete composite bridge |
Location
Location: |
Aegidienberg, Bad Honnef, Rhein-Sieg-Kreis, North Rhine-Westphalia, Germany |
---|---|
Part of: | |
Coordinates: | 50° 39' 51.48" N 7° 18' 51.99" E |
Technical Information
Dimensions
total length | 150 m | |
height above valley floor or water | 12 m |
Quantities
structural steel | 1 100 t | |
concrete volume | 5 165 m³ | |
reinforcing steel | 715 t |
Materials
superstructure |
composite steel-reinforced concrete
|
---|
Participants
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Brückenbauwerke der Neubaustrecke Köln-Rhein/Main. In: Eisenbahntechnische Rundschau ( 2000), pp. 7-12. (2000):
- About this
data sheet - Structure-ID
20001782 - Published on:
19/08/2001 - Last updated on:
05/02/2016