General Information

Beginning of works: December 2003
Completion: August 2006
Duration of works: 32 months
Status: in use

Project Type

Location

Location: , , ,
Coordinates: 50° 23' 23.12" N    7° 42' 20.70" E
Show coordinates on a map

Technical Information

Dimensions

total length 332 m
span lengths 31 m - 40 m - 4 x 55 m - 41 m
number of spans 7
bridge surface 5 395 m²

Quantities

concrete volume 10 135 m²
prestressing steel 118.5 t
reinforcing steel 1 125 t

Cost

overall structure cost of construction Euro 4 800 000
substructure cost of construction Euro 1 000 000
superstructure cost of construction Euro 3 800 000

Materials

deck prestressed concrete
piers reinforced concrete
abutments reinforced concrete

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20048940
  • Published on:
    04/11/2009
  • Last updated on:
    13/02/2018
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine