General Information
Completion: | 28 November 2015 |
---|---|
Status: | in use |
Project Type
Function / usage: |
Motorway bridge / freeway bridge |
---|---|
Material: |
Prestressed concrete bridge |
Structure: |
Multiple T-section girder bridge |
Plan view: |
Structurae Plus/Pro - Subscribe Now! |
Support conditions: |
for registered users |
Construction method: |
Precast girders with cast-in-situ slab Structurae Plus/Pro - Subscribe Now! |
Material: |
Structurae Plus/Pro - Subscribe Now! |
Location
Location: |
Almere, Flevoland, Netherlands Naarden, North Holland, Netherlands |
---|---|
Next to: |
Hollandse Brug (1969)
|
Coordinates: | 52° 19' 31.54" N 5° 8' 21.30" E |
Technical Information
Dimensions
main span | 50.5 m | |
total length | 354 m | |
bridge surface | ca. 11 200 m² | |
total width | 32 m |
Materials
piers |
reinforced concrete
|
---|---|
deck slab |
reinforced concrete
|
abutments |
reinforced concrete
|
girders |
prestressed concrete
|
Participants
Owner
Design
Design-build-finance-maintain contractor
Structural engineering
Checking engineering
- Peter Heijmans (checking engineer)
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Bauwerke im Zuge des PPP-Projektes SAAone in den Niederlanden. Drei Brücken über den Amsterdam-Rhein-Kanal und die zweite Hollandse Brug. In: Brückenbau, v. 9, n. 1-2 ( 2017), pp. 108-115. (2017):
- About this
data sheet - Structure-ID
20082861 - Published on:
17/05/2022 - Last updated on:
05/08/2022