General Information
Completion: | 2008 |
---|---|
Status: | in use |
Project Type
Structure: |
Haunched girder bridge Box girder bridge |
---|---|
Function / usage: |
Road bridge |
Material: |
Prestressed concrete bridge Structurae Plus/Pro - Subscribe Now! |
Location
Technical Information
Dimensions
total length | 700 m | |
approach viaduct 1 | ||
---|---|---|
span lengths | 2 x 31.5 m | |
number of spans | 2 | |
approach viaduct 2 | ||
span lengths | 11 x 31.5 m | |
number of spans | 11 | |
main bridge | ||
span lengths | 45 m - 70 m - 45 m |
Materials
deck |
prestressed concrete
|
---|---|
piers |
reinforced concrete
|
abutments |
reinforced concrete
|