Footbridge for an HIV Orphanage

General Information

Completion: 2005
Duration of works: 1.5 months
Status: in use

Project Type

Location

Location: ,

Technical Information

Dimensions

total length 54 m
span 41 m
cables diameter 22 mm
sag 5 m
deck width 1.5 m
pylons height 6 m
height 10 m
suspenders diameter 12 mm

Cost

cost of construction Euro 12 100

Materials

cables steel wire
foundations reinforced concrete
pylons steel
anchorages reinforced concrete
deck flooring wood

Chronology

December 2005

Completion.