• DE
  • EN
  • FR
  • International Database and Gallery of Structures

Advertisement

Share

Follow

Footbridge for an HIV Orphanage

General Information

Completion: 2005
Duration of works: 1.5 months
Status: in use

Project Type

Structure: Suspension bridge
Function / usage: Pedestrian bridge (footbridge)

Location

Location: ,

Technical Information

Dimensions

total length 54 m
span 41 m
cables diameter 22 mm
sag 5 m
deck width 1.5 m
pylons height 6 m
height 10 m
suspenders diameter 12 mm

Cost

cost of construction Euro 12 100

Materials

cables steel wire
foundations reinforced concrete
pylons steel
anchorages reinforced concrete
deck flooring wood

Chronology

December 2005

Completion.

Advertisement

Relevant Web Sites

  • About this
    data sheet
  • Structure-ID
    20017719
  • Date created
    08/09/2005
  • Last Update
    05/02/2016