General Information
Project Type
Function / usage: |
Motorway bridge / freeway bridge |
---|---|
Structure: |
Haunched girder bridge |
Material: |
Prestressed concrete bridge |
Structure: |
main bridge: Box girder bridge |
Construction method: |
main bridge: Balanced cantilever method |
Material: |
Structurae Plus/Pro - Subscribe Now! |
Structure: |
approach viaduct: T-section girder bridge |
Construction method: |
approach viaduct: Movable Scaffolding System |
Location
Location: |
Eltmann, Haßberge (Kreis), Bavaria, Germany |
---|---|
Crosses: |
|
Carries: |
|
Part of: | |
Next to: |
Eltmann Bridge (1987)
|
Coordinates: | 49° 58' 38.62" N 10° 38' 54.10" E |
Technical Information
Dimensions
total length | 1 055 m | |
bridge surface | 14 500 m² | |
total width | 14.288 m | |
deck | roadway / carriageway width | 11.50 m |
piers | height | 8 - 10 m |
approach viaduct | ||
---|---|---|
deck depth | 2.20 m | |
span lengths | 10 x 40.405 m - 40.005 m - 38.393 m | |
deck width | 13.775 m | |
number of spans | 12 | |
deck slab thickness | 22 - 52 cm | |
main bridge | ||
deck depth | 3.80 - 7.50 m | |
span lengths | 72.661 m - 98.509 m - 147.09 m - 150.00 m - 104.192 m | |
number of spans | 5 | |
web thickness | 0.45 - 0.60 m |
Quantities
deck | concrete volume | 12 200 m³ |
prestressing steel | 640 t |
Cost
cost of construction | ca. Euro 18 000 000 |
Materials
deck |
prestressed concrete
|
---|---|
piers |
reinforced concrete
|
abutments |
reinforced concrete
|
Participants
Owner
Client
Alternative design
Structural engineering
Checking engineering
- Bernd Brandt (checking engineer)
Contractor
Prestressing
Construction supervision
Relevant Web Sites
There currently are no relevant websites listed.
- About this
data sheet - Structure-ID
20025840 - Published on:
06/01/2007 - Last updated on:
05/02/2016