General Information
Completion: | 1887 |
---|---|
Status: | in use |
Project Type
Function / usage: |
Road bridge |
---|---|
Structure: |
Truss bridge |
Material: |
Timber bridge Structurae Plus/Pro - Subscribe Now! |
Location
Location: |
Clarence, Canterbury, New Zealand |
---|---|
Crosses: |
|
Technical Information
Dimensions
span lengths | 18.3 m - 4 x 36.6 m | |
number of spans | 5 |
Materials
piers |
concrete-filled cast-iron tubes
|
---|---|
truss |
timber
|
Notes
Several floods have caused damage to the bridge so that the repaired trusses vary in design from the original trusses.
Participants
Currently there is no information available about persons or companies having participated in this project.
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Bridging the Gap. Early Bridges in New Zealand 1830-1939. Reed Books, Auckland (New Zealand), pp. 19. (2001):
- About this
data sheet - Structure-ID
20024721 - Published on:
03/11/2006 - Last updated on:
05/02/2016