Beginning of works: June 2006
Completion: December 2007
Duration of works: 19 months
Status: in use

Project Type

Structure: Arch bridge
Function / usage: Bicycle and pedestrian bridge
Material: Steel bridge

Location

Location: , ,
Crosses:
  • Autobahn A4
Coordinates: 50° 52' 42.00" N    11° 37' 46.00" E
Show coordinates on a map

Technical Information

Dimensions

total length 59.00 m
arch arch span 45.804 m
depth 0.70 - 1.90 m
deck walkway width 2 × 2.00 m

Quantities

substructure concrete volume 242 m³
reinforcing steel 19.5 t
superstructure structural steel 55 t
concrete volume 160 m³
reinforcing steel 36 t

Cost

cost of construction Euro 700 000

Materials

girder steel
arch steel
deck slab reinforced concrete
abutments reinforced concrete
cross beams steel
springings reinforced concrete

Advertisement

Participants

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20064776
  • Published on:
    20/03/2013
  • Last updated on:
    05/02/2016