General Information
Project Type
Structure: |
Arch dam Gravity dam |
---|---|
Function / usage: |
Hydroelectric dam / plant |
Material: |
Concrete dam |
Location
Location: |
Montalegre, Vila Real, Portugal |
---|---|
Impounds: |
|
Coordinates: | 41° 44' 22.77" N 7° 51' 28.60" W |
Technical Information
Dimensions
height | 94 m | |
retained water volume | 569.0 hm³ | |
crest length | 1 897 m | |
dam volume | 1 117 000 m³ |
Materials
dam structure |
concrete
|
---|
Excerpt from Wikipedia
Alto Rabagão Dam (Portuguese:Barragem do Alto Rabagão) is a concrete dam on the Rabagão River, a left tributary of the Cávado River. It is located in Peneda-Gerês National Park, in the municipality Montalegre, in Vila Real District, Portugal.
Construction of the dam began in 1957. The dam was completed in 1964. It is owned by Companhia Portuguesa de Produção de Electricidade (CPPE). The dam is used for power production.
Dam
Alto Rabagão Dam is a 94 m tall (height above foundation) and 1,970 m long concrete dam, which is composed of a arch dam in the center and gravity dams on both sides. Ist crest altitude is 880 m. The volume of the dam is 1,117,000 m³. The dam contains a crest spillway with 2 gates (maximum discharge 500 m³/s) and a bottom outlet (maximum discharge 360 m³/s).
Reservoir
At full reservoir level of 880 m (maximum flood level of 880.1 m) the reservoir of the dam has a surface area of 22.12 km² and ist total capacity is 568.69 mio. m³. Ist active capacity is 557.92 (550 or 550.1) mio. m³. Minimum operating level is 829 m. With the 550.1 mio. m³ water 973.1 GWh can be produced.
Power plant
The pumped-storage hydroelectric power plant went operational in 1964. It is owned by CPPE, but operated by EDP. The plant has a nameplate capacity of 68 (72) MW. Ist average annual generation is 85.2 (83 95 or 97) GWh.
The power station is located downstream and contains 2 reversible Francis turbine-generators with 36.75 MW (45 MVA), each in an underground powerhouse. The turbine rotation is 428 rpm. The minimum hydraulic head is 129 m, the maximum 185 m. Maximum flow per turbine is 25.7 m³/s. When pumping, each of the pumps has a maximum energy consumption of 31.7 MW and can pump 18 m³/s. The pumps are operated independently of the Francis turbines.
As lower reservoir for Alto Rabagão the reservoir of Venda Nova Dam is used.
Text imported from Wikipedia article "Alto Rabagão Dam" and modified on July 23, 2019 according to the CC-BY-SA 4.0 International license.
Participants
Relevant Web Sites
- About this
data sheet - Structure-ID
20012672 - Published on:
03/08/2004 - Last updated on:
10/07/2015