Project Type
Function / usage: |
Motorway bridge / freeway bridge |
---|---|
Material: |
Steel-reinforced concrete composite bridge |
Structure: |
main bridge: Double-cell box grider bridge approach viaduct: T-section girder bridge |
Location
Location: |
Hagen, North Rhine-Westphalia, Germany |
---|---|
Crosses: |
|
Carries: |
|
Part of: |
|
Replaces: |
A 1 Lenne Bridge
|
Coordinates: | 51° 24' 32.77" N 7° 29' 37.01" E |
Technical Information
Dimensions
total length | 195.00 m | |
span lengths | 40.00 m - 53.00 m - 40.00 m - 37.00 m - 25.00 m | |
number of spans | 5 | |
bridge surface | 7 100 m³ | |
total width | 37.61 m | |
deck | roadway / carriageway width | 15.75 m + 14.50 m |
Quantities
foundations | reinforcing steel | 60 t |
total length of piles | 700 m | |
substructure | concrete volume | 2 460 m³ |
reinforcing steel | 290 t | |
superstructure | structural steel | 1 650 t |
concrete volume | 2 600 m³ | |
reinforcing steel | 535 t |
Materials
deck of main bridge |
composite steel-reinforced concrete
|
---|---|
deck of approach viaducts |
prestressed concrete
|
Participants
Owner
Client
Structural engineering
Geotechnical/geological experts
Checking engineering
- Winfried Neumann (checking engineer)
Contractor
Site supervision
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Brücken und Tunnel der Bundesfernstraßen 2010. Bundesministerium für Verkehr, Bau und Stadtentwicklung, Berlin (Germany), pp. 69-94.
- About this
data sheet - Structure-ID
20043212 - Published on:
26/01/2009 - Last updated on:
05/02/2016