PERI formwork systems allowed the concrete core, which is approximately 46m high, to be completed in 10 full height lifts over a period of 10 weeks. This included a week for re-making the shutters, after pour 3, to adjust the height. Not only did the RUNDFLEX circular formwork panels enable safe working at height both inside and outside the core but the CB Climbing Platforms also limited the amount of temporary works that were required