The renewal of the pressure shaft for the Kaunertal high-head hydropower plant in Austria
Author(s): |
Andreas Hammer
Paul Bonapace Rainer Maldet Oswin Schüller |
---|---|
Medium: | journal article |
Language(s): | English |
Published in: | Steel Construction, December 2013, n. 4, v. 6 |
Page(s): | 257-264 |
DOI: | 10.1002/stco.201310042 |
Abstract: |
A new steel-lined pressure shaft and surge tank are being constructed for the existing Kaunertal high-head hydropower plant. The inclined shaft with a diameter of 4.3 m is approx. 1430 m long and is designed for a pressure head of 100 bar. The steel lining is fully embedded and installed inside the precast concrete segmental lining, which was earlier erected as the tunnelling work progressed. Steel design criteria take into account that the internal pressure is shared between the pipe steel and the rock mass according to the stiffness ratio of lining and rock mass. |
Keywords: |
brittle fracture pressure shaft fracture mechanics steel lining material requirements
|
Available from: | Refer to publisher |
- About this
data sheet - Reference-ID
10069448 - Published on:
15/12/2013 - Last updated on:
13/08/2014