Author(s): (Department of Civil Engineering, Faculty of Engineering, Universitas Indonesia, Kampus Baru UI Depok, Depok 16424, Indonesia)
ORCID (Research Center for Transportation Technology, National Research and Innovation Agency, Tangerang Selatan 15314, Indonesia)
(Faculty of Civil and Environmental Engineering, Institut Teknologi Bandung, Bandung 40132, Indonesia)
(Department of Industrial Engineering, Faculty of Engineering, University of Andalas, Kampus Limau, Padang 25163, Indonesia)
(Department of Civil Engineering, Faculty of Engineering, Universitas Indonesia, Kampus Baru UI Depok, Depok 16424, Indonesia)
Medium: journal article
Language(s): English
Published in: Infrastructures, , n. 4, v. 8
Page(s): 74
DOI: 10.3390/infrastructures8040074
Abstract:

In Indonesia, the CoS for power supply increased from Rp. 1025 to Rp. 1334/KWh from 2016 to 2021, respectively; this indicates an inefficient process in electricity provision. One contributing factor to this inefficiency is the existence of many high speed diesel (HSD)-fueled power plants. These are distributed across the Indonesian archipelago with a supply chain that only uses sea transportation. The absence of an economical small-scale LNG (SS-LNG) supply chain also demonstrates the inadequate infrastructure for distributing LNG to refineries. This study aims to analyze the probability of risks that occur in SS-LNG supply chains in the Indonesian archipelago. The analytical methods used are descriptive statistical analysis and Delphi analysis through in-depth interviews and Focus Group Discussions (FGD) with experts. Results showed that the SS-LNG supply chain process in Indonesia includes LNG loading, unloading, shipping, picking, storage, regasification, and distribution. There are 30 risk indicators that may occur, with the highest risks including ship accidents, equipment damage, lack of transport ships, bad weather, earthquakes, tsunami, poor safety cultures, and low levels of safety leadership. These risk indicators can be used in implementing SS-LNG.

Copyright: © 2023 the Authors. Licensee MDPI, Basel, Switzerland.
License:

This creative work has been published under the Creative Commons Attribution 4.0 International (CC-BY 4.0) license which allows copying, and redistribution as well as adaptation of the original work provided appropriate credit is given to the original author and the conditions of the license are met.

  • About this
    data sheet
  • Reference-ID
    10722697
  • Published on:
    22/04/2023
  • Last updated on:
    10/05/2023
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine