Predicting the project time and costs using EVM based on gray numbers

Author(s):


Medium: journal article
Language(s): English
Published in: Engineering, Construction and Architectural Management, , n. 9, v. 26
Page(s): 2107-2119
DOI: 10.1108/ecam-07-2018-0291
Abstract:

Purpose

The purpose of this paper is to determine the project completion time and cost under non-deterministic conditions using interval gray numbers (IGNs).

Design/methodology/approach

The earned value management (EVM) method based on the IGN has been developed.

Findings

The EVM method based on the IGN has been verified by a numerical example that can be applied to construction projects.

Practical implications

The EVM method, based on the gray numbers, reduces the budget and time shortage risk. Also, using this method, the managers would not be restricted to provide very exact values in their progress reports in the non-deterministic conditions.

Originality/value

One notable and significant point in all projects during the execution process is to estimate the project completion time and cost. However, non-deterministic conditions for both planned and actual physical completion percentage of projects have not been considered for predicting the project completion time and cost in the literature. Therefore, the novelty of this paper is the prediction of project completion time and cost under non-deterministic conditions using IGN.

Structurae cannot make the full text of this publication available at this time. The full text can be accessed through the publisher via the DOI: 10.1108/ecam-07-2018-0291.
  • About this
    data sheet
  • Reference-ID
    10576838
  • Published on:
    26/02/2021
  • Last updated on:
    26/02/2021
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine