Author(s): |
Marwan Nader
|
---|---|
Medium: | journal article |
Language(s): | Spanish |
Published in: | Hormigón y acero, 22 December 2022, n. 298, v. 73 |
Page(s): | 5-12 |
DOI: | 10.33586/hya.2022.3000 |
Abstract: |
The new Samuel De Champlain Bridge Project (the “Project”) is one of the largest crossings in NorthAmerica. The signature span is an asymmetrical cable-stayed bridge featuring a 240 m main span overthe St. Lawrence Seaway. The Project was subjected to a fast-tracked schedule of only 48 months fromdesign to opening. The design-build team made innovative use of precast concrete, modular segments,and erection sequencing to meet the Project timeline, while overcoming the site-specific hazards andsevere winters unique to Montréal. |