0
  • DE
  • EN
  • FR
  • International Database and Gallery of Structures

Advertisement

A Model for Evaluating the Risk Effects on Construction Project Activities

Author(s):


Medium: journal article
Language(s): Latvian
Published in: Journal of Civil Engineering and Management, , n. 7, v. 25
Page(s): 687-699
DOI: 10.3846/jcem.2019.10531
Abstract:

Cost overruns and time delays are considered to be very important challenges for the majority of construction projects. These challenges are typically attributed to their associated risks. Due to the risky and uncertain nature of construction projects, an increasing amount of attention is given to estimating and overcoming cost overruns and time delays. New techniques are being developed to help project managers to contractually complete projects within cost and time constraints. The objective of this study was to develop a new qualitative and quantitative risk analysis model that can be employed for construction projects. The proposed model, which is based on a fuzzy logic tool, consists of two modules for assessing risk factors that affect the main construction activities and computing the expected cost overruns and time delays that are associated with these risks. Using numerous logical rules, the model applies the probability of occurrences and impacts of the risks on the cost and time of the main activities. The Spearman and Kendall correlation coefficient tests are applied to verify and select a suitable membership function. Using four proposed membership functions, the results of these tests confirmed that the triangle membership function is suitable for the model. The model is verified by application to HVAC system activities in two actual construction projects, which serve as case studies. Two different methods are proposed and applied to quantify the cost overruns and time delays. The first method is based on determining the cost overruns and time delay values for each activity according to their weight in the system. Triple premise rules are proposed and applied in the second method, which is established to relate all activities. The results from the second method are more accurate compared with the first method based on actual data from the case study projects. In addition, the results demonstrated that the proposed model can be used to quantify the expected cost overrun and time delays in construction project activities and can be generalized and implemented in different construction activities.

Structurae cannot make the full text of this publication available at this time. The full text can be accessed through the publisher via the DOI: 10.3846/jcem.2019.10531.
  • About this
    data sheet
  • Reference-ID
    10354136
  • Published on:
    13/08/2019
  • Last updated on:
    13/08/2019
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine