An Integrated Approach of Simulation and Regression Analysis for Assessing Productivity in Modular Integrated Construction Projects

Author(s): ORCID
ORCID
ORCID
Medium: journal article
Language(s): English
Published in: Buildings, , n. 11, v. 12
Page(s): 2018
DOI: 10.3390/buildings12112018
Abstract:

Many nations across the globe face the challenge of housing deficit. Modular integrated construction (MiC), which has the highest level of prefabrication among off-site construction manufacturing (OSM), has been adopted as a fast and reliable construction method to address the housing deficit. Previous studies have assessed the productivity of the prefabrication stage of MiC, while investigations into the productivity of the MiC installation process with the consideration of pragmatic factors, especially for high-rise buildings, are lacking in the literature. Therefore, this study contributes by (1) developing a discrete-event simulation (DES) model to assess the productivity of MiC installation while considering pragmatic factors (e.g., weather conditions, topography, work dimension, etc.) and management conditions (e.g., workers’ motivation, training, equipment maintenance, etc.); (2) developing a mathematical model to understand the relationship between productivity and various resources utilized in MiC installation. After verifying and validating the DES model, it was applied to a case study in Hong Kong. A sensitivity analysis using a full factorial experiment design was conducted to identify the parameters (e.g., number of trucks, tower cranes, different crews) that significantly affect a number of performance measures, such as the project duration, productivity, and total costs. Furthermore, the mathematical model shows high prediction accuracy, as the mean absolute percentage error is 8.93%. This study would help construction practitioners in their decision-making process, while planning a project by providing them with a model that can predict the productivity of the MiC installation process before and during the project implementation.

Copyright: © 2022 by the authors; licensee MDPI, Basel, Switzerland.
License:

This creative work has been published under the Creative Commons Attribution 4.0 International (CC-BY 4.0) license which allows copying, and redistribution as well as adaptation of the original work provided appropriate credit is given to the original author and the conditions of the license are met.

  • About this
    data sheet
  • Reference-ID
    10699853
  • Published on:
    10/12/2022
  • Last updated on:
    10/05/2023
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine