Instandsetzung von Bauten des Kraftwerks Meliti, Griechenland, nach einem Brand

Author(s):




Medium: journal article
Language(s): German
Published in: Stahlbau, , n. 1, v. 83
Page(s): 47-56
DOI: 10.1002/stab.201410134
Abstract:

Structural rehabilitation of the power plant Meliti, Greece after fire.

The power plant Meliti in Northern Greece is a 300 MW power station that uses lignite as fuel. On the 25th of July 2014 a fire broke out in the conveyor belt that transports the coal to the bunker. The fire resulted in damages in the 240 m long steel conveyor bridge and the concrete bunker structure. The conveyor bridge was repaired without scaffolding temporary supports by exchanging the damaged parts and the connection media with new. The bunker was subjected to local damages that were rehabilitated by application of FRP sheets and FRP wraps. The plant was in operation in two months after it was fully rehabilitated.

Keywords:
FRP reinforcement Reinforcing strengthening lamella rehabilitation fire damage sheet wrap coal bunker
Available from: Refer to publisher
Structurae cannot make the full text of this publication available at this time. The full text can be accessed through the publisher via the DOI: 10.1002/stab.201410134.
  • About this
    data sheet
  • Reference-ID
    10069687
  • Published on:
    20/01/2014
  • Last updated on:
    13/08/2014
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine