Abstract: |
The Cityringen (The City Circle) project is the latest phase of the metro system in Copenhagen, Denmark. The phase comprises the construction of 17 new stations, three shafts, a control and maintenance centre and 16.5 km of twin-tube tunnel excavated by four Earth Pressure Balance TBMs. The design and build contract was awarded in January 2011 and inauguration is planned for late 2018. |
Keywords: |
groundwater control urban area settlement minimisation monitoring
|