Beamless or beam-supported building floors

Is buildability knowledge the missing link to improving productivity?

Author(s):
Medium: journal article
Language(s): English
Published in: Engineering, Construction and Architectural Management, , n. 3, v. 24
Page(s): 537-552
DOI: 10.1108/ecam-11-2014-0147
Abstract:

Purpose

Due to a dearth of quantitative research into buildability factors affecting formwork labour productivity ofin situreinforced concrete construction, the purpose of this paper is to establish a distinct point of departure from the prevalent qualitative trend of buildability research practices by exploring, quantifying and comparing the influence of the two widely used design schemes; namely, beamless and beam-supported building floors, on formwork labour productivity.

Design/methodology/approach

A considerable quantity of relevant formwork labour productivity data associated with each building floor configuration was collected from projects sharing similar characteristics. The data were analysed to determine the statistical significance of the difference between the two labour productivity “means” of the sample sets representing both populations. Regression analyses were further carried out to assess the impact of floor area on labour efficiency.

Findings

The results obtained show a statistically significant difference between the two means of formwork labour productivity achieved, where the efficiency of “forming” the beam-supported floor type is, on average, lower by 57 per cent than that of the beamless configuration. The outcomes further demonstrate a significant influence of building floor area on the productivity of the form-working operation.

Practical implications

The findings can provide designers with feedback on how well their decisions consider the requirements of buildability principles, and the consequences thereto on labour productivity. The depicted pattern of results may, moreover, provide guidance to estimators and project managers for reasonable cost estimation, effective planning and efficient labour utilisation.

Originality/value

The general guidelines available for buildability improvement lack the supporting quantitative evidence, and thus are often viewed with scepticism, especially amongst design practitioners. On the contrary, the quantitative outcomes reported in this study are based on rigorous methodology, hence can be used as a supporting reference to “formalise” the specific buildability knowledge of the activity explored.

Structurae cannot make the full text of this publication available at this time. The full text can be accessed through the publisher via the DOI: 10.1108/ecam-11-2014-0147.
  • About this
    data sheet
  • Reference-ID
    10576566
  • Published on:
    26/02/2021
  • Last updated on:
    26/02/2021
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine