An analysis of the delivery challenges influencing public-private partnership in housing projects

The case of Tanzania

Author(s):


Medium: journal article
Language(s): English
Published in: Engineering, Construction and Architectural Management, , n. 2, v. 25
Page(s): 202-240
DOI: 10.1108/ecam-12-2016-0261
Abstract:

Purpose

The purpose of this paper is twofold: first, to identify and rank the challenges influencing the delivery of the housing public-private partnership (HPPP) in Tanzania; and second, to suggest solutions in the form of a conceptual public-private partnership (PPP) framework model that will address the identified challenges and boost the chances of success.

Design/methodology/approach

Using a convergent parallel (concurrent) mixed method approach, data were collected from 28 stakeholders involved with HPPP projects in Tanzania using a hand-delivered and e-mail survey and 13 semi-structured interviews with public and private sector respondents. The quantitative data included subjecting the 19 challenges as identified from the literature to parametric tests such as one-samplet-tests and descriptive statistics tests such as measures of central tendencies and frequency analysis through Statistical Package for Social Sciences (SPSS 22.0). Qualitative data employed content analysis. The research was further underpinned by a number of theoretical perspectives such as Gidden’s structuration theory, contingency theory, relational and equity theory.

Findings

The top five ranked challenges influencing the delivery of HPPP were “inadequate PPP skills and knowledge”; “poor contracting and tendering documents”; “inadequate project management”; “inadequate legal framework”; and “misinformation on financial capacity of private partners”. The least six ranked and most significant challenges based on the one-sample (single)t-tests were as follows: “Poor risk allocation”; “inexperienced private partner”; “unequal qualification and contributions of expertise”; “poor enabling environment to attract competent partners”; “inadequate mechanisms for recovery of private investors’ capital”; and “high costs in procuring PPP projects”. The qualitative study further confirmed the challenges and cited the reason for the failure of joint venture projects as the lack of motivation for undertaking similar PPP projects. Despite the increased awareness of PPP projects and associated marginal benefits, the main impediment to the uptake and delivery of PPP housing projects remained the lack of skills and expertise.

Research limitations/implications

The proposed framework model is not yet tested, but since this paper is part of the ongoing research, the next stage involves the testing and validation of the model. Future studies could test the applicability of the proposed framework in other HPPP projects in Tanzania, and in other similar developing countries. Second, the validated framework can contribute towards addressing similar challenges as well as providing guidance. The proposed framework model is not yet tested, but since this paper is part of the ongoing research, the next stage involves the testing and validation of the model. Furthermore, recommendation for future research is to test the alignment of the identified challenges to the proposed remedial solutions across the five phases within the proposed PPP framework with a number of case studies.

Practical implications

The identified challenges were used to form the basis of the framework presented in this paper. Furthermore, these provide useful information, thus leading to increased awareness to enable successful delivery of HPPP in Tanzania. Similarly, both the government and policy makers could use the findings as the basis for re-examining the existing PPP policy and regulations, and reflecting on the existing situation with a view to improving the delivery of future HPPP projects.

Originality/value

The empirical study is among the first that identifies and ranks the challenges of PPP for housing projects delivery within the Tanzanian context. The identification of the challenges enabled their ranking, resulting in the mapping out of the most critical challenges. Furthermore, using the Gidden’s structuration theory, the study illustrates how institution mechanisms (structures) address these delivery challenges, thus influencing the implementation of HPPP in Tanzania, and how individual stakeholders (human agents or agency) are able to make choices (advocated solutions) in dealing with the challenges. More so, these constraints (challenges) as identified and viewed through the contingency and equity theoretical lenses form the foundation for developing the PPP conceptual framework. The proposed framework would thus serve as a mechanism for providing practical solutions as well as reducing the level of severity of the identified challenges.

Geographic Locations

Structurae cannot make the full text of this publication available at this time. The full text can be accessed through the publisher via the DOI: 10.1108/ecam-12-2016-0261.
  • About this
    data sheet
  • Reference-ID
    10576624
  • Published on:
    26/02/2021
  • Last updated on:
    26/02/2021
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine