Shear test on full scale auxiliary pier columns used in the viaduct construction process

 Shear test on full scale auxiliary pier columns used in the viaduct construction process
Author(s): , ,
Presented at IABSE Symposium: Large Structures and Infrastructures for Environmentally Constrained and Urbanised Areas, Venice, Italy, 22-24 September 2010, published in , pp. 754-755
DOI: 10.2749/222137810796063616
Price: € 25.00 incl. VAT for PDF document  
ADD TO CART
Download preview file (PDF) 0.03 MB

The paper describes an original technology used for onsite shear tests. The test determines the shear stiffness in both the principle directions of an auxiliary system employed during accelerated c...
Read more

Bibliographic Details

Author(s):


Medium: conference paper
Language(s): English
Conference: IABSE Symposium: Large Structures and Infrastructures for Environmentally Constrained and Urbanised Areas, Venice, Italy, 22-24 September 2010
Published in:
Page(s): 754-755 Total no. of pages: 8
Page(s): 754-755
Total no. of pages: 8
Year: 2010
DOI: 10.2749/222137810796063616
Abstract:

The paper describes an original technology used for onsite shear tests. The test determines the shear stiffness in both the principle directions of an auxiliary system employed during accelerated construction process of the prefabricated bridge. The auxiliary pier system is constituted by the coupling of two temporary truss towers working as auxiliary pier columns to carry and erect the prefabricated pieces during the bridge construction procedure. By this experimental investigation we are able to redesign the whole temporary auxiliary systems affected by some faults in the flanged connections. A good correspondence between numerical and experimental investigation was obtained.

Keywords:
structural monitoring design assisted by tests