Contributing human and organizational factors to the collapse of the FC Twente stadium roof
|
Bibliographic Details
Author(s): |
Karel Terwel
(Delft University of Technology, The Netherlands)
|
||||
---|---|---|---|---|---|
Medium: | conference paper | ||||
Language(s): | English | ||||
Conference: | IABSE Congress: Structural Engineering for Future Societal Needs, Ghent, Belgium, 22-24 September 2021 | ||||
Published in: | IABSE Congress Ghent 2021 | ||||
|
|||||
Page(s): | 1565-1571 | ||||
Total no. of pages: | 7 | ||||
DOI: | 10.2749/ghent.2021.1565 | ||||
Abstract: |
In 2011 the city of Enschede was shocked by the collapse of the roof of an extension for the FC Twente stadium. The structure collapsed during construction and two fatalities and nine injuries were recorded. The cantilevering steel roof structure was covered with corrugated steel sheets and stabilized by bracings. Investigation showed that the structure was already loaded with the finishing structure before it was completed and stabilized. Contributing influencing human and organizational factors to the incident were the tight schedule resulting in a flawed construction sequence. Furthermore, there was too little attention to the way of execution during design, unjustified trust between parties resulting in inadequate coordination, checking and allocation of responsibilities. |
||||
Keywords: |
forensic engineering human and organizational factors causes of failure
|
||||
Copyright: | © 2021 International Association for Bridge and Structural Engineering (IABSE) | ||||
License: | This creative work is copyrighted material and may not be used without explicit approval by the author and/or copyright owner. |