General Information

Beginning of works: 1981
Completion: 1983
Status: in use

Project Type

Location

Location: ,
Location description:

Connects the mainland of Koweit to the island of Bubiyan.

Coordinates: 29° 36' 23.59" N    48° 9' 58.56" E

Technical Information

Dimensions

total length 2 380 m
span lengths 61 x 40.16 m - 53.80 m
number of spans 62

Materials

superstructure prestressed concrete

Chronology

August 1990
- February 1991

Sustains heavy damage in the Gulf War. 4 spans destroyed.

1995

The safety of the structure is ensured.

Participants

Design
Consulting
Consulting engineers
Construction
Project direction
Reconstruction
Contractor

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20000613
  • Date created
    22/01/2000
  • Last Update
    05/02/2016