Airport Düsseldorf-International

General Information

Beginning of works: 1997
Completion: 2003
Status: in use

Project Type

Function / usage: Airport

Location

km Name

Technical Information

There currently is no technical data available.

Chronology

11 April 1996

During welding works as part of upgrading and maintenance of terminal building B, sparks start a smoldering fire in the ventilation ducts. Heavy and toxic smoke fills the entire terminal building, 17 people die asphyxiated. The building is unusable for months. Terminal A remains unaffected, C only slightly.

November 1996

Terminal building C is re-opened.

1997

Construction begins for a long-distance train station.

March 1997

Architectural design competition to replace terminal building B is won by JSK Architekten.

December 1998

Demolition of Terminal B begins. Parking garage no. 1 is also demolished to make room for the extended new terminal.

1999

Construction for new underground parking at terminal B begins.

17 March 1999

Marlies Smeets, mayor of Düsseldorf, and Wolfgang Clement, prime minister of North Rhine-Westphalia, lay the first stone for the new terminal building.

28 May 2000

The new long distance train station begins railroad services. Up to 300 trains a day stop at the station.

1 July 2001

Terminal B is opened for passenger service. President Johannes Rau is present during the inauguration.

1 July 2002

The SkyTrain monorail begins service between the main terminals and the long-distance railroad station.

Participants

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    10000114
  • Date created
    11/07/2002
  • Last Update
    16/05/2015