Transfer of Technology for Prestressed Concrete Bridges
Auteur(s): |
M. Fujiwara
S. T. Maung |
---|---|
Médium: | article de revue |
Langue(s): | anglais |
Publié dans: | Structural Engineering International, août 1992, n. 3, v. 2 |
Page(s): | 199-201 |
DOI: | 10.2749/101686692780628479 |
Abstrait: |
Myanmar engineers were first introduced to the technology of the construction of prestressed concrete girder bridges in 1967 when introduced to 30-m-span prestressed concrete girder bridges by Canadian engineers. The Bridge Engineering Training Center Project enabled Myanmar engineers to build the Thuwunna Bridge with a span of around 100 m, albeit under the guidance of the Japanese engineers stationed full-time at the site. The subsequent construction of Ngawun Bridge, with a similar span, provided the opportunity for Myanmar engineers to develop the technology acquired on the Thuwunna Bridge Project. |