Auteur(s): , ORCID
Présenté pendant IABSE Symposium: Towards a Resilient Built Environment Risk and Asset Management, Guimarães, Portugal, 27-29 March 2019, publié dans , pp. 1058-1064
DOI: 10.2749/guimaraes.2019.1058
Prix: € 25,00 incl. TVA pour document PDF  
AJOUTER AU PANIER
Télécharger l'aperçu (fichier PDF) 0.8 MB

The temporary supports erection method is the most common way of building cable-stayed bridges. In this technique the bridge deck is first built over a set of temporary and permanent supports. Then...
Lire plus

Détails bibliographiques

Auteur(s): (University of Castilla-La Mancha, UCLM, Ciudad Real, Spain)
ORCID (Universitat Politècnica de Catalunya, BarcelonaTech, UPC, Barcelona, Spain)
Médium: papier de conférence
Langue(s): anglais
Conférence: IABSE Symposium: Towards a Resilient Built Environment Risk and Asset Management, Guimarães, Portugal, 27-29 March 2019
Publié dans:
Page(s): 1058-1064 Nombre total de pages (du PDF): 7
Page(s): 1058-1064
Nombre total de pages (du PDF): 7
DOI: 10.2749/guimaraes.2019.1058
Abstrait:

The temporary supports erection method is the most common way of building cable-stayed bridges. In this technique the bridge deck is first built over a set of temporary and permanent supports. Then, during the tensioning process, the stays are successively placed and tensioned by the jacks and the deck is raised from the temporary supports. Several variants of this method are the launching of the bridge and the rotation method. This paper proposes an algorithm to calculate and to control the construction of such bridges when the strand by strand tensioning technique is used. It is based on the unstressed length of the stays concept. The use of such concept enables a fast and direct simulation of construction stages by analysing independent Finite Element Models. As there is no need of superposition of models it is a very convenient way for construction supervision.

Mots-clé:
Ponts à haubans