Innovative Technology at the Deconstruction of Bridges
|
Détails bibliographiques
Auteur(s): |
Karl-Heinz Reintjes
|
||||
---|---|---|---|---|---|
Médium: | papier de conférence | ||||
Langue(s): | anglais | ||||
Conférence: | IABSE Conference: Bridges and Structures Sustainability - Seeking Intelligent Solutions, Guangzhou, China, 8-11 May 2016 | ||||
Publié dans: | IABSE Conference, Guangzhou, China, 8 – 11 May 2016 | ||||
|
|||||
Page(s): | 1006-1013 | ||||
Nombre total de pages (du PDF): | 8 | ||||
Année: | 2016 | ||||
DOI: | 10.2749/222137816819259419 | ||||
Abstrait: |
Special methods had to be developed for the deconstruction of two bridges in the course of the widening of the motorway A7 in Hamburg. At one bridge blocks of ultra high strength concrete with steel fibres are used as temporary anchoring of the prestress tendons. At the other bridge the old concrete superstructure is removed by a special incremental launching backwards. |