Burlington Bay Skyway Hanger Fail-Safe System

 Burlington Bay Skyway Hanger Fail-Safe System
Auteur(s): ORCID, ,
Présenté pendant IABSE Congress: The Evolving Metropolis, New York, NY, USA, 4-6 September 2019, publié dans , pp. 2720-2725
DOI: 10.2749/newyork.2019.2720
Prix: € 25,00 incl. TVA pour document PDF  
AJOUTER AU PANIER
Télécharger l'aperçu (fichier PDF) 0.18 MB

The Burlington Bay Skyway was built in 1954 and rehabilitated in the 1980s. A continuous three span truss rises from below the deck up over the roadway across the 151 m central span over a navigati...
Lire plus

Détails bibliographiques

Auteur(s): ORCID (Ontario Ministry of Transportation)
(Ontario Ministry of Transportation)
(Ontario Ministry of Transportation)
Médium: papier de conférence
Langue(s): anglais
Conférence: IABSE Congress: The Evolving Metropolis, New York, NY, USA, 4-6 September 2019
Publié dans:
Page(s): 2720-2725 Nombre total de pages (du PDF): 6
Page(s): 2720-2725
Nombre total de pages (du PDF): 6
DOI: 10.2749/newyork.2019.2720
Abstrait:

The Burlington Bay Skyway was built in 1954 and rehabilitated in the 1980s. A continuous three span truss rises from below the deck up over the roadway across the 151 m central span over a navigational channel into Hamilton Harbour. The deck system hangs from the truss and the consequences of a hanger impact could be severe and include prolonged closure, impediment of the navigation channel, and could trigger a progressive collapse of the suspended deck system arising from simply supported stringers and floor trusses. The regional economic impact of bridge closure on one of Ontario’s major arteries is considerable.

The Ontario Ministry of Transportation (MTO) is adding redundancy trusses to transfer the load from the deck system to adjacent hangers in the event of hanger loss. Each truss runs longitudinally below the edge of the deck through the main span, within the depth of the existing transverse floor trusses. The proactive retrofit improves redundancy of the deck system and keeps the bridge serviceable and safe after hanger loss, in-line with current code requirements.