Work continuity constraints in repetitive project scheduling considering soft logic

Auteur(s):


Médium: article de revue
Langue(s): anglais
Publié dans: Engineering, Construction and Architectural Management, , n. 6, v. 28
Page(s): 1713-1738
DOI: 10.1108/ecam-11-2019-0595
Abstrait:

Purpose

Repetitive projects play an important role in the construction industry. A crucial point in scheduling this type of project lies in enabling timely movement of crews from unit to unit so as to minimize the adverse effect of work interruptions on both time and cost. This paper aims to examine a repetitive scheduling problem with work continuity constraints, involving a tradeoff among project duration, work interruptions and total project cost (TPC). To enhance flexibility and practicability, multi-crew execution is considered and the logic relation between units is allowed to be changed arbitrarily. That is, soft logic is considered.

Design/methodology/approach

This paper proposes a multi-objective mixed-integer linear programming model with the capability of yielding the optimal tradeoff among three conflicting objectives. An efficient version of the e-constraint algorithm is customized to solve the model. This model is validated based on two case studies involving a small-scale and a practical-scale project, and the influence of using soft logic on project duration and total cost is analyzed via computational experiments.

Findings

Using soft logic provides more flexibility in minimizing project duration, work interruptions and TPC, especial for non-typical projects with a high percentage of non-typical activities.

Research limitations/implications

The main limitation of the proposed model fails to consider the learning-forgetting phenomenon, which provides space for future research.

Practical implications

This study assists practitioners in determining the “most preferred” schedule once additional information is provided.

Originality/value

This paper presents a new soft logic-based mathematical programming model to schedule repetitive projects with the goal of optimizing three conflicting objectives simultaneously.

Structurae ne peut pas vous offrir cette publication en texte intégral pour l'instant. Le texte intégral est accessible chez l'éditeur. DOI: 10.1108/ecam-11-2019-0595.
  • Informations
    sur cette fiche
  • Reference-ID
    10577050
  • Publié(e) le:
    26.02.2021
  • Modifié(e) le:
    02.09.2021
 
Structurae coopère avec
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine