Optimized crew selection for scheduling of repetitive projects

Auteur(s):

Médium: article de revue
Langue(s): anglais
Publié dans: Engineering, Construction and Architectural Management, , n. 6, v. 28
Page(s): 1517-1540
DOI: 10.1108/ecam-10-2019-0590
Abstrait:

Purpose

The purpose of this paper is to identify optimum crew formations at unit execution level of repetitive projects that minimize project duration, project cost, crew work interruptions and interruption costs, simultaneously.

Design/methodology/approach

The model consists of four modules. The first module quantifies uncertainties associated with the crew productivity rate and quantity of work using the fuzzy set theory. The second module identifies feasible boundaries for activity relaxation. The third module computes direct cost, indirect cost and interruption costs, including idle crew cost as well as mobilization and demobilization costs. The fourth module identifies near-optimum crew formation using a newly developed multi-objective optimization model.

Findings

The developed model was able to provide improvements of 0.2, 16.86 and 12.98% for minimization of project cost, crew work interruptions and interruption costs from US$1,505,960, 8.3 days and US$8,300, as recently reported in the literature, to US$1,502,979, 6.9 days and US$7,222, respectively, without impacting the optimized project duration.

Originality/value

The novelty of this paper lies in its activity-relaxation free float that considers the effect of postponing early finish dates of repetitive activities on crew work interruptions. The introduced new float allows for calculating the required crew productivity rate that minimizes crew work interruptions without delaying successor activities and without impacting the optimized project duration. It safeguards against assignment of unnecessary costly resources.

Structurae ne peut pas vous offrir cette publication en texte intégral pour l'instant. Le texte intégral est accessible chez l'éditeur. DOI: 10.1108/ecam-10-2019-0590.
  • Informations
    sur cette fiche
  • Reference-ID
    10577033
  • Publié(e) le:
    26.02.2021
  • Modifié(e) le:
    02.09.2021
 
Structurae coopère avec
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine