Optimized crew selection for scheduling of repetitive projects

Autor(en):

Medium: Fachartikel
Sprache(n): Englisch
Veröffentlicht in: Engineering, Construction and Architectural Management, , n. 6, v. 28
Seite(n): 1517-1540
DOI: 10.1108/ecam-10-2019-0590
Abstrakt:

Purpose

The purpose of this paper is to identify optimum crew formations at unit execution level of repetitive projects that minimize project duration, project cost, crew work interruptions and interruption costs, simultaneously.

Design/methodology/approach

The model consists of four modules. The first module quantifies uncertainties associated with the crew productivity rate and quantity of work using the fuzzy set theory. The second module identifies feasible boundaries for activity relaxation. The third module computes direct cost, indirect cost and interruption costs, including idle crew cost as well as mobilization and demobilization costs. The fourth module identifies near-optimum crew formation using a newly developed multi-objective optimization model.

Findings

The developed model was able to provide improvements of 0.2, 16.86 and 12.98% for minimization of project cost, crew work interruptions and interruption costs from US$1,505,960, 8.3 days and US$8,300, as recently reported in the literature, to US$1,502,979, 6.9 days and US$7,222, respectively, without impacting the optimized project duration.

Originality/value

The novelty of this paper lies in its activity-relaxation free float that considers the effect of postponing early finish dates of repetitive activities on crew work interruptions. The introduced new float allows for calculating the required crew productivity rate that minimizes crew work interruptions without delaying successor activities and without impacting the optimized project duration. It safeguards against assignment of unnecessary costly resources.

Structurae kann Ihnen derzeit diese Veröffentlichung nicht im Volltext zur Verfügung stellen. Der Volltext ist beim Verlag erhältlich über die DOI: 10.1108/ecam-10-2019-0590.
  • Über diese
    Datenseite
  • Reference-ID
    10577033
  • Veröffentlicht am:
    26.02.2021
  • Geändert am:
    02.09.2021
 
Structurae kooperiert mit
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine