Nps Composite Beams and Columns Used for the Odense University Hospital

Auteur(s): (Tecnostrutture S.r.l.)
(Odense Hospital Project Team Joint Venture I/S)
Médium: article de revue
Langue(s): anglais
Publié dans: ce/papers, , n. 1, v. 6
Page(s): 554-565
DOI: 10.1002/cepa.1936
Abstrait:

This document presents the case study of the Odense University Hospital, built with the NPS steel‐concrete composite frame. This is one of the most challenging projects currently in Europe: 250,000 square meters to be built in just over three years. The client has taken up the challenge of respecting timeframe and budget by focusing on offsite construction and digitalization of processes. Time constrains, safety and sustainability are the three main drivers of the project. Among these, the strict delivery time represents the main critical aspect. The expected turnkey delivery in 2022 assumed the choice of an extremely simple and fast construction method. Further advantages of using steel‐concrete composite structures with reference to the Odense University Hospital Case are explained.

Structurae ne peut pas vous offrir cette publication en texte intégral pour l'instant. Le texte intégral est accessible chez l'éditeur. DOI: 10.1002/cepa.1936.
  • Informations
    sur cette fiche
  • Reference-ID
    10767453
  • Publié(e) le:
    17.04.2024
  • Modifié(e) le:
    17.04.2024
 
Structurae coopère avec
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine