General Information

Beginning of works: 2008
Completion: 28 January 2016
Status: in use

Project Type

Structure: main span:
Through arch bridge
Function / usage: Road bridge
Material: approach viaduct:
Prestressed concrete bridge
main span:
Steel-concrete composite bridge

Location

Location: , , ,
Coordinates: 37° 17' 45.19" N    22° 1' 32.67" E
Show coordinates on a map

Technical Information

Dimensions

total length 490 m
arch span 300 m
piers height max. 35.0 m

Materials

piers reinforced concrete
deck of main span composite steel-reinforced concrete
arch steel
deck of approach viaduct prestressed concrete
abutments reinforced concrete