New NY Bridge – Super Crane’s First Lift
http://www.NewNYBridge.com One of the world’s largest floating cranes successfully completed the first of many enormous lifts for the New NY Bridge project on April 24, 2015, following months of planning and preparation. In a carefully coordinated three-and-a-half hour operation on the Hudson River between Westchester and Rockland counties, the I Lift NY super crane hoisted and set one of the project’s largest precast concrete pile caps weighing in at 600 tons. Owned by Tappan Zee Constructors, LLC, the design-build contractor for the New York State Thruway Authority, the super crane’s extraordinary capabilities save time and money while enhancing quality and safety by allowing large sections of the bridge to be pre-fabricated off-site and shipped by barge to the construction zone.
|