Rapid Bridge Replacement – Learning from the USA

 Rapid Bridge Replacement – Learning from the USA
Auteur(s):
Présenté pendant IABSE Conference: Engineering the Past, to Meet the Needs of the Future, Copenhagen, Denmark, 25-27 June 2018, publié dans , pp. 233-239
DOI: 10.2749/copenhagen.2018.233
Prix: € 25,00 incl. TVA pour document PDF  
AJOUTER AU PANIER
Télécharger l'aperçu (fichier PDF) 0.16 MB

The IStructE Pai Lin Li Travel Award funded the author for an investigation into current practice precast concrete construction in the USA. The Federal Highways Administration (FHWA) in the USA h...
Lire plus

Détails bibliographiques

Auteur(s): (Arup, London, UK)
Médium: papier de conférence
Langue(s): anglais
Conférence: IABSE Conference: Engineering the Past, to Meet the Needs of the Future, Copenhagen, Denmark, 25-27 June 2018
Publié dans:
Page(s): 233-239 Nombre total de pages (du PDF): 7
Page(s): 233-239
Nombre total de pages (du PDF): 7
DOI: 10.2749/copenhagen.2018.233
Abstrait:

The IStructE Pai Lin Li Travel Award funded the author for an investigation into current practice precast concrete construction in the USA. The Federal Highways Administration (FHWA) in the USA has invested heavily in research into precast concrete construction through its Accelerated Bridge Construction (ABC) programme. The FHWA’s research has had a focus on innovative techniques for joining structural precast concrete elements together.

Grouted splice couplers and Ultra-High Performance Concrete are the two key enabling techniques that were investigated in this research. The replacement of 6 36m span bridges over Interstate 78 in Pennsylvania used these techniques and completed each bridge replacement in 40 days. This paper investigates the development of these techniques, the benefits they could have on the UK construction industry and what actions need to be taken to realise those benefits.