Design and Construction of Hwamyung Bridge
|
Détails bibliographiques
Auteur(s): |
Kwang-Soo Kim
Eun-Chul Lee Chun-Soo Lee Eu-Kyeong Cho |
||||
---|---|---|---|---|---|
Médium: | papier de conférence | ||||
Langue(s): | anglais | ||||
Conférence: | 18th IABSE Congress: Innovative Infrastructures – Towards Human Urbanism, Seoul, Korea, 19-21 September 2012 | ||||
Publié dans: | IABSE Congress Seoul 2012 | ||||
|
|||||
Page(s): | 849-856 | ||||
Nombre total de pages (du PDF): | 8 | ||||
DOI: | 10.2749/222137912805111230 | ||||
Abstrait: |
Hwamyung Bridge over the Nakdong River is the largest cast-in place concrete cable stayed bridge in Korea with a center span of 270m and side span of 115m each. The stay-cables are spaced at 6.8m along the box girder and arranged in a semi-harp configuration. They are anchored at central single towers with vertical leg extending 65m above the deck. With the closure of center span in November 2010, the erection of cable and box girder, which is a major portion of the bridge construction, was completed. |