BIM-Based Resource Tradeoff in Project Scheduling Using Fire Hawk Optimizer (FHO)

Auteur(s): ORCID
ORCID

ORCID
Médium: article de revue
Langue(s): anglais
Publié dans: Buildings, , n. 9, v. 12
Page(s): 1472
DOI: 10.3390/buildings12091472
Abstrait:

Project managers should balance a variety of resource elements in building projects while taking into account many major concerns, including time, cost, quality, risk, and the environment. This study presents a framework for resource trade-offs in project scheduling based on the Building Information Modeling (BIM) methodology and metaheuristic algorithms. First, a new metaheuristic algorithm called Fire Hawk Optimizer (FHO) is used. Using project management software and the BIM process, a 3D model of the construction is created. In order to maximize quality while minimizing time, cost, risk, and CO2 in the project under consideration, an optimization problem is created, and the FHO’s capability for solving it is assessed. The results show that the FHO algorithm is capable of producing competitive and exceptional outcomes when it comes to the trade-off of various resource options in projects.

Copyright: © 2022 by the authors; licensee MDPI, Basel, Switzerland.
License:

Cette oeuvre a été publiée sous la license Creative Commons Attribution 4.0 (CC-BY 4.0). Il est autorisé de partager et adapter l'oeuvre tant que l'auteur est crédité et la license est indiquée (avec le lien ci-dessus). Vous devez aussi indiquer si des changements on été fait vis-à-vis de l'original.

  • Informations
    sur cette fiche
  • Reference-ID
    10692622
  • Publié(e) le:
    23.09.2022
  • Modifié(e) le:
    10.11.2022
 
Structurae coopère avec
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine