Assessment and Measurement of the Forsmo Bridge, Sweden
Auteur(s): |
Ib Enevoldsen
C. Pedersen F. Axhag O. Johansson B. Töyrä |
---|---|
Médium: | article de revue |
Langue(s): | anglais |
Publié dans: | Structural Engineering International, novembre 2002, n. 4, v. 12 |
Page(s): | 254-257 |
DOI: | 10.2749/101686602777965117 |
Abstrait: |
This paper focuses on the discrepancy that may occur between finite element modelling (FEM) and on-site strain measurements. This is based on practical experience the from assessment of the Forsmo Bridge; a 263 m long and 50 m high riveted steel-truss-arch railway bridge completed in 1912. The three-dimensional FE-modelling is described and typical problems are outlined. Results from strain-gauge measurements are included. The FE-model is updated and lessons learned are described. Recommendations for modelling are given and it is concluded that on-site measurements and model updating can be crucial for assessment of sufficient accuracy. |