Innovative Means and Methods for the New Champlain Bridge
|
Bibliografische Angaben
Autor(en): |
Gonzalo Osborne
(Abstract)
Jeff Rogerson (Abstract) Fréderic Guitard (Abstract) André Mylocopos (Abstract) |
||||
---|---|---|---|---|---|
Medium: | Tagungsbeitrag | ||||
Sprache(n): | Englisch | ||||
Tagung: | IABSE Symposium: Engineering the Future, Vancouver, Canada, 21-23 September 2017 | ||||
Veröffentlicht in: | IABSE Symposium Vancouver 2017 | ||||
|
|||||
Seite(n): | 2098-2105 | ||||
Anzahl der Seiten (im PDF): | 8 | ||||
Jahr: | 2017 | ||||
DOI: | 10.2749/vancouver.2017.2098 | ||||
Abstrakt: |
Signature on the Saint Lawrence Construction (SSLC), a consortium comprised of SNC-Lavalin inc., Flatiron Constructors Canada, Dragados USA and EBC, is mandated to build the New Champlain Bridge Corridor Project (NCBCP). Significant challenges include:
This paper discusses the following innovative construction methods used for the New Champlain Bridge (NCB):
These erection systems were developed and selected to suit the specific challenges of the project, including speed of construction, maintenance of shipping and environmental protection areas. |
||||