Reviewing Construction Schedule Float Management
Autor(en): |
Jyh-Bin Yang
|
---|---|
Medium: | Fachartikel |
Sprache(n): | Englisch |
Veröffentlicht in: | The Open Construction and Building Technology Journal, Dezember 2017, n. 1, v. 11 |
Seite(n): | 1-13 |
DOI: | 10.2174/1874836801711010001 |
Abstrakt: |
As the complexity in construction projects increased, simply managing the obtained float values and critical path(s) by the CPM method usually results in more difficult schedule control and, consequently, in incorrect decision making due to non-realistic float values. This study thoroughly reviewed various float types in the literature and professional project management systems, and discussed five managerial essentials and three proactive strategies on mitigating challenging float-related problems based on the perspective of managing schedules by controlling floats. With some comments and suggestions, the outcomes of this study not only improve the knowledge level on schedule management but also provide a better understanding of float management to improve the quality of schedule management. |
Copyright: | © 2017 Jyh-Bin Yang, |
Lizenz: | Dieses Werk wurde unter der Creative-Commons-Lizenz Namensnennung 4.0 International (CC-BY 4.0) veröffentlicht und darf unter den Lizenzbedinungen vervielfältigt, verbreitet, öffentlich zugänglich gemacht, sowie abgewandelt und bearbeitet werden. Dabei muss der Urheber bzw. Rechteinhaber genannt und die Lizenzbedingungen eingehalten werden. |
0.42 MB
- Über diese
Datenseite - Reference-ID
10381111 - Veröffentlicht am:
22.11.2019 - Geändert am:
02.06.2021