Chirajara Bridge Collapse

 Chirajara Bridge Collapse
Autor(en): , ORCID, , ,
Beitrag für IABSE Conference: Risk Intelligence of Infrastructures, Seoul, South Korea, 9-10 November 2020, veröffentlicht in , S. 18-32
DOI: 10.2749/seoul.2020.018
Preis: € 25,00 inkl. MwSt. als PDF-Dokument  
ZUM EINKAUFSWAGEN HINZUFÜGEN
Vorschau herunterladen (PDF-Datei) 0.17 MB

On January 15, 2018 at 11:49, the west pylon (B) of the cable-stayed Chirajara Bridge collapsed during construction of the bridge girder. The crossing is located approximately 20km NW of Villavicen...
Weiterlesen

Bibliografische Angaben

Autor(en): (Aarhus University, Aarhus, Denmark)
ORCID (Yokohama National University, Yokohama, Japan)
(Leonhardt Andrä und Partner, Stuttgart, Germany)
(Leonhardt Andrä und Partner, Stuttgart, Germany)
(Leonhardt Andrä und Partner, Stuttgart, Germany)
(KHO Consult, Copenhagen, Denmark)
(ES Consult, Copenhagen, Denmark)
(Rambøll, Esbjerg, Denmark)
(Rambøll, Esbjerg, Denmark)
(Smoltczyk und Partner, Stuttgart, Germany)
Medium: Tagungsbeitrag
Sprache(n): Englisch
Tagung: IABSE Conference: Risk Intelligence of Infrastructures, Seoul, South Korea, 9-10 November 2020
Veröffentlicht in:
Seite(n): 18-32 Anzahl der Seiten (im PDF): 15
Seite(n): 18-32
Anzahl der Seiten (im PDF): 15
DOI: 10.2749/seoul.2020.018
Abstrakt:

On January 15, 2018 at 11:49, the west pylon (B) of the cable-stayed Chirajara Bridge collapsed during construction of the bridge girder. The crossing is located approximately 20km NW of Villavicencio, Colombia. The collapse led to the total destruction of Pylon B, together with the erected span of the bridge girder. Authorities reported nine fatalities resulting from the collapse. Shortly thereafter, the project insurer QBE Segures, Colombia commissioned an independent investigation into the collapse of the bridge, through loss adjusters ONC Adjusters, Bogotá, Colombia. An international team of engineering experts was assembled to undertake the investigation. The investigation was completed in August, 2018. Key findings and recommendations from the investigation are presented herewith.