Bridge 6 (Brighton Goods) Reconstruction

 Bridge 6 (Brighton Goods) Reconstruction
Autor(en): ,
Beitrag für IABSE Conference: Assessment, Upgrading and Refurbishment of Infrastructures, Rotterdam, The Netherlands, 6-8 May 2013, veröffentlicht in , S. 612-613
DOI: 10.2749/222137813806548541
Preis: € 25,00 inkl. MwSt. als PDF-Dokument  
ZUM EINKAUFSWAGEN HINZUFÜGEN
Vorschau herunterladen (PDF-Datei) 0.49 MB

The paper describes the civil engineering works needed to replace the bridge structure originally built in 1890 as part of the London, Chatham and Dover Railway providing an interchange at this sit...
Weiterlesen

Bibliografische Angaben

Autor(en):

Medium: Tagungsbeitrag
Sprache(n): Englisch
Tagung: IABSE Conference: Assessment, Upgrading and Refurbishment of Infrastructures, Rotterdam, The Netherlands, 6-8 May 2013
Veröffentlicht in:
Seite(n): 612-613 Anzahl der Seiten (im PDF): 8
Seite(n): 612-613
Anzahl der Seiten (im PDF): 8
Jahr: 2013
DOI: 10.2749/222137813806548541
Abstrakt:

The paper describes the civil engineering works needed to replace the bridge structure originally built in 1890 as part of the London, Chatham and Dover Railway providing an interchange at this site between Kent bound services and the many siding lines, depot and locomotive works that used to be present under the bridge.

The scheme involved the construction of five individual cast in situ reinforced concrete boxes and associated permanent way alignment design of all seven tracks (three above and four below) to suit the geometry of the new arrangement, which was successfully implemented during planned line blockages of the railway.

The structural integrity of the existing masonry piers that supported the existing superstructure had to be maintained at all times during the phased construction of each box.

The existing structure was demolished during a nine day all lines closure of the Kent (Chatham) Lines over the Christmas 2011 period, with the new structure in operation for the New Year. The remaining civil works were completed shortly after in February 2012.

Stichwörter:
Rekonstruktion Eisenbahnbrücke Stahlbeton Bodenverbesserung Bewertung