Temperature Control for Mass Concrete Construction of Wentang Bridge 5# Pier Pile Cap in Winter Construction

Autor(en):



Medium: Fachartikel
Sprache(n): Englisch
Veröffentlicht in: Journal of Physics: Conference Series, , n. 1, v. 2476
Seite(n): 012079
DOI: 10.1088/1742-6596/2476/1/012079
Abstrakt:

In order to ensure the construction quality of mass concrete structures in winter, and avoid and prevent harmful temperature cracks of mass concrete, a calculation method of temperature field of hydration heat in winter based on finite element method is proposed in this paper. First, the three-dimensional finite element model of the temperature field of hydration heat is established; Then, the temperature variation of winter hydration heat temperature field of Wentang Bridge is calculated through experiments. The results show that the maximum measured temperature of the core point is 44.2 °C, and the corresponding calculated temperature is 53.7 °C. The maximum internal and external temperature difference measured is 24.7 °C, and the corresponding calculated temperature is 22.4°C. The research results prove that the calculation model can better simulate the concrete hydration process.

Structurae kann Ihnen derzeit diese Veröffentlichung nicht im Volltext zur Verfügung stellen. Der Volltext ist beim Verlag erhältlich über die DOI: 10.1088/1742-6596/2476/1/012079.
  • Über diese
    Datenseite
  • Reference-ID
    10777587
  • Veröffentlicht am:
    12.05.2024
  • Geändert am:
    12.05.2024
 
Structurae kooperiert mit
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine